Current Projects
MR – 12 Main Replacement Project:
- The project, which has been awarded to CB utility of Bristol RI, has been on hold due to supply-chain related issues related to availability of water works materials.
- Work is to include approximately 14,000 feet predominately in Pawtucket service area. CB has mobilized on site and anticipates beginning in early November 2021 and working through mid-2022.
- It is anticipated that work will be complete in mid-2022 barring further supply issues.